SA Release with Pick-up Date or Delivery Date Instead of the delivery date customer and vendor can send the pick-up date, which is the time at which a freight forwarder picks up the required materials or products from the vendor.
If the customer sends the pick-up date in the scheduling agreement (SA) release, the vendor can process the dates accordingly as well as confirm the quantities on the basis of the pick-up date.
In the
procurement process
, you can use the
Date Key
in the
Release Creation Profile
that you assign to procurement scheduling agreements to define which date you want to send to your customer in the release.(See also
Release Creation Profile
)
In the
sales process
the
Date Key
of the schedule line is displayed in the master data, in the release data or in the release and confirmation history of sales scheduling agreement releases and taken into account during shipment scheduling.
In the procurement process you define whether you want to the send the pick-up date or the delivery date in the releases that you send to your vendors. You do this in Customizing forSupply Chain Planningunder
in the
Date Key
field.
For sales scheduling agreement items that you plan in the SAP APO system, you must also select
ATP Check
in the integration model, so that the material is scheduled in SAP APO.This ensures that when scheduling agreement releases are created in the SAP R/3 system over the CIF, the same dates (delivery date, goods issue date, loading date, material availability date, and so on) are determined as in the SAP APO system.
When the release is created – starting from the availability date (of the receipt in the product view) – the system determines the pick-up date or delivery date that is to be transmitted in the release:
Pick-up Date = Availability Date – Goods Receipt Processing Time – Move Time
Delivery Date = Availability Date – Goods Receipt Processing Time
On the procurement side, it is always the delivery date that is sent to the linked SAP R/3 system and displayed in the scheduling agreement, independently of whether you send the pick-up date or the delivery date to your vendor.
On the sales side, the material availability date is determined on the basis of the pick-up or delivery date.
Starting from the desired delivery date backward scheduling takes place in order to determine the material availability date.
Material Availability Date = Delivery Date – Shipment Duration – Loading Time – Pick/Pack Time
Starting from the pick-up date (GI date) backward scheduling takes place in order to determine the material availability date.
Material Availability Date = GI Date – Loading Time – Pick/Pack Time

The material availability date is determined on the basis of the conditions that you have defined in the master data for transportation and shipment scheduling.
You can simulate shipment scheduling in master data maintenance for the sales scheduling agreement (
Shipment Scheduling
tab page).
For more information see Transportation and Shipment Scheduling under Global Availability Check (Global ATP) .
If the operative and forecast/planning delivery schedules contain different date keys then the date key of the most recent delivery schedule is used during the generation of the due delivery schedule.
In the sales scheduling agreement in the linked SAP R/3 system the calculated dates are displayed in the scheduling agreement on the
Shipping
tab page. If your customer sends the pick-up date then the delivery date and the goods issue date are identical.
For more information see the SAP Library underSAP Advanced Planner and Optimizer (SAPAPO