Release Creation Profile (APO Scheduling Agreement) The release creation profile is used to specify the following for operative and forecast/planning delivery schedules issued against APO scheduling agreements :
How the horizon of the scheduling agreement (SA) release (delivery schedule) is determined
How schedule lines from the past are handled in the SA releases
Which event triggers the release creation process (changes to schedule lines and/or the next transmission date being arrived at)
Whether a tolerance check is carried out for releases that are created due to changes
Whether and how many “last deliveries” the vendor is informed of in the SA release
That tolerances are to be checked and, if necessary, SA releases stopped in the event of changes in the overall delivery schedule situation.
Example
The settings in the release creation profile can have the following effects for an external procurement relationship for a scheduling agreement item:
Your vendor receives operative delivery schedules on a weekly basis. Each schedule contains lines covering the next three weeks. In addition, the vendor receives a forecast/planning delivery schedule at the beginning of each month, which covers the following three months.
If the scheduling agreement schedule lines have changed significantly, updated SA releases can be sent to the vendor.
Note
The release creation profile that you maintain in the APO system is only valid for APO scheduling agreements.
For releases against an OLTP scheduling agreement, which are created in the OLTP system, it is the release creation profile in the OLTP system that is applicable.
For more information on the prerequisites, see Prerequisites for the APO Scheduling Agreement .
You can define the following in the release creation profile:
Area |
For each SA release type (operative or F/P schedule) you define: |
|---|---|
Layout |
|
Modes of creation |
|
Tolerances |
|
Last Deliveries |
|
Dynamic stopping |
|
You assign the release creation profile to an external procurement relationship for an APO scheduling agreement and in this way you define how SA releases are generated for this SA item.
Note
When scheduling agreement data is transferred from your OLTP system to the SAP APO system via the
SAP APO Core Interface (CIF)
, the release creation profile is not included in the data transmitted. You must create a new release creation profile for APO scheduling agreements in your SAP APO system and assign it to the relevant SA item (of procurement category
APO scheduling agreement
) in the external procurement relationship.
If you wish to use forecast/planning (F/P) delivery schedules in addition to operative delivery schedules, you must specify this in the external procurement relationship (in the
Scheduling Agreement
with Forecast
field on the
Scheduling Agreement
tab page).
The settings for F/P delivery schedules from the release creation profile are only taken into account in the SA release creation process if you have specified in the external procurement relationship that F/P delivery schedules are to be created.
Example
You wish to provide your vendor not only with data on your concrete short-term product requirements (using operative delivery schedules) but also with data on your more tentative longer-term requirements (using forecast/planning delivery schedules). Therefore, you select the
Scheduling Agreement with Forecast
indicator for this item in the external procurement relationship.
You define the release creation profile in Customizing for
Advanced Planning and Optimization (SAP APO),
under
You then assign this release creation profile to the external procurement relationship for the scheduling agreement item on the
Scheduling Agreement
tab page.