 Calculation of Table of Periods for a Resource

Use

You can use this function to simulate the determination of the periods for grouping the components.

Integration

The calculation of the table of periods is also possible in Customizing during maintenance of the period profile . You start the function by accessing a particular period profile and choosing the Simulation for a resource function key.

Prerequisites

  • You have maintained a period profile .

  • You have maintained the factory calendar for a location.

  • You have created a line resource and a shift sequence for this resource.

Features

The calculation of a table of periods is illustrated in the following example:

You have set the period profile as follows:

Length

Unit of Length

Unit of Aggregation

-

-

Year

1

Month

Month

1

Month

Week

1

Week

Day

1

Day

Shift

In this example, a resource with a shift sequence of 3 shifts is used (6.00 to 14.00, 14.00 to 22.00, 22.00 to 6.00 hrs). You set a start date of 8 December 1999, for example. The simulation then produces the following result for the period profile described above:

Shifts

  • Period 1: 8 December 1999, 06.00 to 13.59

  • Period 2: 8 December 1999, 14.00 to 21.59

  • Period 3: 22.00 on 8 December 1999 to 05.59 on 9 December.

Days

  • Period 4: 9 December 1999, 06.00 to 05.59

  • Period 5: 10 December 1999, 06.00 to 05.59

  • Period 6: 11 December 1999, 06.00 to 05.59 and so on up to 18 December 1999 at 05.59.

Weeks

  • Period 11: 06.00 on 20 December 1999 to 05.59 on 27 December 1999

  • Period 12: 06.00 on 27 December 1999 to 05.59 on 03 January 2000

  • Period 13: 06.00 on 13 January 2000 to 05.59 on 10 January 2000

  • Period 14: 06.00 on 10 January 2000 to 05.59 on 17 January 2000

  • This then continues with weeks up to 05.59 on 31 January.

  • Period 17: 06.00 on 31 January 2000 to 05.59 on 01 February 2000

Months

Periode 18:01. Feb. 2000 6.00 to 01. Mar. 2000 5.59 hrs

A month always starts with the first workday and ends on the first workday of the following month.

Activities

  1. Choose Start of the navigation path Rapid Planning Matrix Next navigation step Tools Next navigation step Table of Periods Next navigation step Calculate Table of Periods for Resource End of the navigation path .

    The initial screen appears.

  2. Enter the line resource,location, planning version, table of periods, and a start date and choose .