Cost Center (Detail): Analysis - Activity Quantity - Plan/Actual
Technical name: 0CCA_C04_Q0001
If you want to modify this query, note the special features of the 0CCA_C04
CO-OM-CCA: Activity Type Quantities and Prices InfoCubeUse
This query provides the cost accountant and the cost center manager with an overview of the costs and activity quantities provided by a cost center in planning and actual data during the reporting time frame.

This query is contained in the
For background information on the concept of queries, see
Queries in Controlling.Filters
InfoObject |
Description |
0CO_AREA |
Controlling area (variable 0P_COAR; single value entry, required) |
0COSTCENTER |
Cost center (variable 0P_CCTR) |
0FISCVARNT |
Fiscal year variant (SAP exit variable 0P_FVAEX) |
User-Defined Characteristics
InfoObject |
Description |
0FISCPER |
Fiscal year/period (variable 0I_FPER) |
Rows
InfoObject |
Description |
0ACTTYPE |
Activity type |
Columns
InfoObject |
Description |
Activity quantity: Plan |
Plan activity quantity in the reporting timeframe |
Activity quantity: Actual |
Actual activity quantity in the reporting timeframe |
Activity quantity: Variance |
Difference between actual and plan activity quantity |
Activity quantity: Variance (%) |
Percentage variance between actual and plan activity quantity with reference to the plan |
Capacity: Plan |
Plan capacity in the reporting timeframe |
Capacity: Actual |
Actual capacity in the reporting timeframe |
Capacity: Variance |
Difference between actual and plan capacity |
Capacity: Variance (%) |
Percentage variance between actual and plan capacity with reference to the plan |
Scheduled activity: Plan |
Scheduled activity quantity (plan) in reporting timeframe |
Scheduled activity: Actual |
Scheduled activity quantity (actual) in reporting timeframe |
Scheduled activity: Variance |
Difference between scheduled activity (actual) and scheduled activity (plan) |
Scheduled activity: Variance % |
Percentage variance between scheduled actual and plan activity with reference to the plan |
Output: Plan |
Plan output quantity in the reporting timeframe |
Output: Actual |
Actual output quantity in the reporting timeframe |
Output: Variance |
Difference between actual and plan output quantity |
Output: Variance % |
Percentage variance between actual and plan output with reference to the plan |