Specifying the Maximum Scheduling DurationThe system cancels scheduling or rescheduling of operations or orders by default after a certain number of scheduling steps (corresponding to a scheduling duration of approximately 10 minutes). This can occur when the system has to consider many dependencies during scheduling or rescheduling; for example, relationships between operations. The maximum scheduling duration refers to the scheduling or rescheduling of the selected operations and to all necessary subsequent rescheduling. If the system cancels scheduling, no operations or orders are scheduled or rescheduled.
You can set another maximum scheduling duration in the detailed scheduling strategy .