Entering content frameFunction documentation Display and Processing of Test Dates Locate the document in its SAP Library structure

Use

If you not only want to display the test dates that were determined during scheduling, but also want to process these dates, you can manually intervene in the scheduling process. There are several different reasons why you might want to do this:

Activities

To manually process the test dates as described above, refer to the following information:

Leaving content frame