Unplanned Activities in the Stability Study
Overview
Over the course of a stability study, you may need to perform certain activities or tasks that you cannot plan in advance, but which you perform "ad hoc", as the need arises. Examples of such activities may include the following scenarios:
This section of the stability study documentation contains information that describes the following unplanned activities:
Testing unplanned inspection characteristics for a stability inspection lot during results recording