Entering content frameProcedure documentation Creating a Preliminary Cost Estimate for a Manufacturing Order Locate the document in its SAP Library structure

Procedure

To manually create a preliminary cost estimate for a production order, go into the change mode of the production order and choose Order ® Functions ® Calculate costs.

Result

If the cost estimate has no errors, then:

To see the planned costs in the production order, choose Goto ® Costs ® Analysis or Goto ® Costs ® Itemization.

If the cost estimate has errors, the manufacturing order receives the status CSER (Error in cost calculation) The system creates a log to collect the system messages and sorts them according to various criteria.

To access the log, choose Goto ® Logs ® Cost calculation in the production order.

Displaying the Planned Costs

The planned costs for the production order can be displayed in the following forms:

To view the cost planning results, access the production order and choose Goto ® Costs ® Analysis.

This brings up a report showing the following information:

You can display the material numbers by double-clicking on the material costs if you have selected the Material origin indicator in the costing view of the material master record.

Note

The system displays both the planned credits (goods receipts) and the planned debits (material withdrawals, internal activity allocations, overhead, and so forth).

If your production process involves co-products, the planned credit in the order is not displayed.

To view the planned credit of the co-product, go to the information system and access a cost element report. Then choose Extras ® Order items ® On/off.

An itemization categorizes the planned costs by cost element and origin or by costing item. That is, it groups the planned costs according to the individual materials and activities whose costs were calculated when you created the production order. The system generates an itemization when you create the production order.

To display the itemization, access the production order and choose Goto ® Costs ® Cost itemization. You can view other formats of the itemization by choosing Other report. You can display the itemization by operation, for example, where within the operations the costs are in turn subdivided into the internal activity and material consumption.

You can view the itemization directly in the production order. The system calculates it dynamically. It is not possible to view the itemization in the information system.

In joint production, the planned costs are reported according to the material master record at the end of the itemization with item category A.

Cost components assign the cost planning results to groups that you define in Customizing for Product Cost Controlling.

To display the cost components, access the production order and choose Goto ® Costs ® Split.

You define which cost components are created for the order in a cost component structure. The cost component structure is selected through the costing variant in the order header.

When you create a standard cost estimate for the material being produced, the costing results are stored in this form for each material in the BOM. In the product cost estimate, you enter various control parameters for each cost component. This allows you to specify parameters such as what values are included in inventory valuation or profitability analysis.

Only those cost components that are flagged as relevant to inventory valuation are displayed in the preliminary cost estimate for the order.

Since the cost component split is generated dynamically, it can only be displayed directly in the production order. It is not possible to see the cost component split for the preliminary cost estimate of a production order or process order in the Product Cost Controlling Information System.

Note

The cost split in the production order is generated dynamically and is not saved. In sales-order-related production, for example, if you calculate the standard price on the basis of a preliminary cost estimate for the production order, you cannot transfer that cost split to Profitability Analysis.

This cost component split is only generated for the planned costs. The actual costs are not assigned to any cost components.

The cost component split for the production order is not a true cost component split because it is a single-level split. The semifinished products used in the finished products are not broken down into cost components but instead are assigned to the cost component to which the cost element of the semifinished product is assigned. For example, the costs for semifinished products can be shown together with the costs for raw materials in the cost component "material costs".

If the controlling area currency differs from the company code currency, the planned costs for the production order will be updated in both currencies. You can display both currencies in the reports of the information system of Product Cost Controlling.

See also:

Preliminary Cost Estimates for Manufacturing Orders

 

 