Entering content frameProcedure documentationDefining the Working Time for a Position Locate the document in its SAP Library structure

Use

By defining a working time for a position, you are in effect providing a reference value for the time required to complete the tasks associated with the position in question.

When you define a working time manually for a specific position, this overrides the working time provisions defined for a higher-level organizational unit.

Procedure

To assign a working time to a position, proceed as follows:

  1. Access the organizational structure using the Organization view.
  2. Click the root organizational unit, and choose This graphic is explained in the accompanying text.
  3. Click the position for which you want to define a working time, and choose This graphic is explained in the accompanying text.
  4. The Planned Working Time dialog box appears.

  5. Enter a working time manually for the position, or select a standard value for the working time.
  6. Choose This graphic is explained in the accompanying text Check.
  7. To save your entries, choose This graphic is explained in the accompanying text.
Leaving content frame