Creating the Testing Schedule
Use
Once you have specified your storage conditions in the stability study, you can create a testing schedule for the study. When you create the testing schedule, you must know:
When you create the testing schedule, the system creates the testing schedule header and a testing schedule item for each storage condition you specified in the stability study. In doing so, the system automatically uses the storage condition short text as the short text for the testing schedule item.
You can create the testing schedule for a stability study more than once, as long as you have not explicitly completed the testing schedule. For example, if you determine that you have used the wrong strategy or if you have specified additional storage conditions in the stability study, which you do not want to manually enter in the testing schedule, you simply create a new testing schedule. This new testing schedule cannot have the same key as the original one. When you create a new testing schedule, the system checks whether a testing schedule already exists for the study. If so, it sets a deletion flag for the original testing schedule and it also deletes the document that explicitly links this testing schedule to the stability study. You can view this link using the follow-up function Display Objects for Study. The system then creates a new testing schedule for the study with your entries.

When you create a testing schedule, the system proposes the key for the stability study as the key for the testing schedule. This proposal is only made if the key for the stability study lies within a valid external number range for testing schedules. If you create a testing schedule a second time, you must change this proposed value if this key was used for the original testing schedule.
Prerequisites
You have
specified storage conditions in the stability study and created a strategy.Procedure
The initial screen for changing a stability study appears.
The screen for changing the stability study data appears.
A dialog box for creating the testing schedule appears. This dialog box contains proposals for the testing schedule key, short text, maintenance plan category, and inspection type.
Result
A testing schedule has been created, which contains items for all storage conditions in the stability study. You can now
process the testing schedule to assign an inspection plan to each storage condition.