In this step of the IMG, you organize budget structure element types into a hierarchical structure.
In your overall budget, you have budget structure elements called 0001 - Level 1, 0002 - Level 2 and 0003 - Level 3.
Budget structure element 0002 - Level 2 should appear below budget structure element 0001 - Level 1 , and above budget structure element 0003 - Level 3.
In this case, you would define the budget
structure element hierarchy as follows in the hierarchy table:
| BS el.type| Name | Assigned BS el.type |Name |
---------------------------------------------------------------
| 0001 | Level 1 | 0002 |Level 2 |
| 0002 | Level 2 | 0003 |Level 3 |
You must have defined budget structure element types in the previous IMG step.