Requirements Grouping for Individual Project Planning 

Use

Requirements grouping is a planning procedure for projects within material requirements planning.

Requirements grouping for individual project planning enables you to group material requirements that are caused by WBS elements within a project or also cross-project, and plan and procure them together. This enables you to save costs.

Requirements grouping is possible only for operative WBS elements.

Prerequisites

You are using the component Project system for the processing of projects.

Integration

Basically, there are three procedures for planning material requirements in projects in the SAP System:

The system only plans individual requirements. Materials that are required for a project (WBS element) are specifically planned for the project and are procured with reference to the WBS element. The materials in the individual project stock of the WBS element are managed and settled separately from the normal stock. Goods issue only takes place with reference to the WBS element.

This procedure is used to plan finished products and important assemblies.

The material requirements for different WBS elements are combined and jointly planned and procured. If you combine the WBS elements within a project to one grouping WBS element, you will have real individual project stock.

If you use cross-project requirements grouping, the ordering parties must give their consent that the assemblies and components are planned and procured using this procedure.

You can plan and procure materials at subordinate BOM levels that are required in all projects, independently of WBS elements, using make-to-stock production. During the planning run, the system calculates the total requirements of a material in a plant. The material is procured without reference to a WBS element.

These materials are managed in the plant stock and are available for all projects.

Features

The requirements grouping for the materials of different WBS elements are carried out by using one or more grouping WBS elements.

You group all WBS elements of projects from the private sector into one grouping WBS element and combine all WBS elements from the public sector into another grouping WBS element and plan each together.

Requirements grouping in individual project planning has the following features: