BOM Transfer to Project System
Purpose
You transfer a bill of material to Project System to assign its components to network activities and update the assignments. You can find further information in the PS - Project System documentation in
Bill of Material Transfer.If you want to replenish an assembly, which has a long replenishment lead time, before the design of the whole product is complete, you can first transfer this assembly to Project System and generate preliminary requirements. In this situation, please read the notes in
Advance procurement in the PS - Project System component.In the order browser, you can trigger BOM transfer on one of the following levels:
Prerequisites
If you work with variant configuration you have selected the result-oriented order BOM in the
configuration profile for the configurable materials.You have maintained the reference points in the BOM items and in the network. You can find further information in
Maintaining Reference Points in BOM Items and
Maintaining Reference Points in Activities.Apart from this, the general prerequisites for BOM transfer to Project System apply. You can find further information in the PS - Project System documentation in
Bill of Material Transfer.
Process Flow
order analysis, whether one or more assemblies are used several times in the multi-level BOM for a sales order item.
If this is the case, replace the material in the corresponding node in the order browser, before you continue with the next steps. For more information, see
The system transfers the whole tree or sub-tree below the selected node to Project System. If configurable assemblies are contained in the tree or sub-tree, the system determines the configuration and transfers the components, which were selected during
The BOM Transfer screen appears. The data in the selected node is transferred to this screen.
Result
If you start BOM transfer from the order browser, the system determines the quantities of each component as the product of:
See also:
Transferring BOMs to Project System