Set Modification Parameters

This step allows you to define the following central settings for your BOMs:

If you activate validity maintenance, you then have the option of specifying a "valid from" date when maintaining a BOM. If validity maintenance is not active, BOMs are created with the current date or if necessary with the internal system low date (1.1.1990).
If you activate the low date (1.1.1990), this will be proposed as the "valid from" date instead of the current date.
If you deactivate engineering change management, you cannot make any changes in the BOM with a historical record.
You only determine in this step whether or not BOM maintenance can be carried out with engineering change management. You specify in the menu option " Determine history requirement for BOMs " whether the use of engineering change management is compulsory in particular cases.
Here you can define a proposed unit of measurement for the BOM header and the BOM items. Remember that the base unit of measure for equipment BOMs and functional location BOMs is always 'piece'.
You only use this indicator when you have activated the BOM engineering change management.
If you want to maintain BOMs from a CAD system, activate the CAD switch. This switch ensures that an additional field appears in the BOM header and BOM item. This field tells you whether the BOM header or BOM item was maintained from the CAD system.

Note

The modification parameters set here are valid both for material BOMs and equipment BOMs. This is, as a rule, a one-time setting which should not be changed once the system is productive.

Default settings

The following settings are supplied in the standard system:

Recommendation

It is recommended that you use the SAP standard settings.

Activities

Define the central settings for BOMs.