Assemblies with a Long Replenishment Lead Time 
Purpose
It is often necessary to obtain an assembly with a long replenishment
lead-time before the design of the entire product is completed.
In the turbine T-20000 you require an extra coolant pump. You have to start early with the production of the pump so that it is available on time. However, the design of the entire turbine is not yet complete. You can not yet decide at which point you are going to integrate the second pump in the multi-level BOM for the sales order item.
Process Flow
You have already created the sales order.
This type of assembly is referred to as a

When you execute a requirements planning run for the material of the sales order item, only the assemblies that exist in the multi-level BOM are included. If a detached order assembly has a long replenishment lead time, it may be necessary to generate requirements even before the design of the entire product is completed
You have the following options:
See:
Material Requirements Planning for Detached Order AssembliesSee:
BOM Transfer to Project SystemThe system generates planned orders, which you can convert into production orders.
In the order analysis of the order browser, you have an overview of all detached order assemblies for a sales order item. During the design process you decide at which point to insert the detached order assembly into the multi-level BOM.
This causes the detached order assembly to become integrated in the multi-level BOM.
See also:
Detached Order Assembly