Transferring SOP Data to Demand Management Asynchronously, Online
The Transfer Planning Data screen appears.
If you want to check the planning data as independent requirements before it is transferred, do not select the field Invisible transfer.
A warning message appears if the version to be transferred is not the active version.
The Planned Independent Requirements screen appears.
The planned quantities of each material appear.
Note that planned independent requirements are created in the base unit of measure of the material. This may be different than the base unit of measure of the information structure.
If you have changed any of the individual quantities, a message appears asking if you wish to accept the total values.
To transfer the data of multiple materials to Demand Management, use mass processing (see How to Transfer Data to Demand Management with Mass Processing).