Transfer to Demand Management 

Use

You can pass on data planned in Flexible Planning or Standard SOP to Demand Management.

Demand Management determines the requirement dates and requirement quantities for important assemblies and specifies the strategies for planning and producing/procuring finished products. The result of Demand Management is the demand program. The demand program differentiates planned independent requirements and customer independent requirements. It gives the information needed in MPS and MRP for planning at SKU level. The placing of sales orders eventually consumes planned requirements and triggers updating to the Sales Information System. This actual data can then be used as input for future sales planning. For more information, see PP Demand Management.

Prerequisites

The system distributes the data to the appropriate plants in Demand Management on the basis of the quotas you set in Customizing (in Define proportional distribution across plants). You can also make these settings in the Flexible Planning or Standard SOP menu by choosing Settings ® Plant distribution. Plant distribution works as follows:

  1. If a plant or plants can be found for the material in the planning hierarchy, data is transferred to Demand Management for these plants.
  2. If no plant can be found in the planning hierarchy, the system checks to see which plants have been maintained for the material in the material master record. It then checks to see whether distribution quotas have been maintained for the material. If quotas have been maintained, the transfer to Demand Management is based on these quotas.
  3. If no distribution quotas are found for the material, the system checks to see whether you have set generic distribution quotas; that is, distribution quotas that apply to all materials. If so, the transfer to Demand Management is based on these quotas. If generic quotas exist for some but not all plants maintained in the material master record, the system assumes that the distribution quotas of plants without generic quotas are 0.
  4. If no distribution quotas are found at all—neither material-specific nor generic ones—, the system splits the data equally among all the plants in the material master record.

See also:

Plant Distribution Quotas

Features

Independent requirements are created in Demand Management for all materials whose data has been transferred. These independent requirements are created in the base unit of measure of the material. The base unit of measure of the material is not necessarily the same as the base unit of measure of the information structure or the unit in which you planned the material. See also Switching Units in the Planning Table.

You can transfer SOP data to Demand Management in the following ways:

See How to Transfer Data to Demand Management with Mass Processing.

See below.

See below.

Transferring Online, Synchronously and Automatically

You set the following information structure parameters in Customizing for Sales & Operations Planning (in Set parameters of info structures and key figures).

The system creates or overwrites independent requirements in Demand Management every time you save this planning version of the information structure in Flexible Planning.

Transferring Online, Asynchronously and Manually

  1. You choose between the following options:
  1. You make the following general settings:

If you do not make an entry, the system sets the requirements type via the MRP group which is maintained in the material master record.

  1. Depending on the option you chose in step 1, you set one of the following strategies.

Transferring Planning Data from a Single-Level Product Group

Transferring Planning Data of One Material from Standard SOP

Transferring Key Figure Data of One Material from Flexible Planning

This key figure must be a quantity key figure.

See also:

Transferring SOP Data to Demand Management Asynchronously, Online