Reporting Point Backflush for Stock Materials 

Use

It makes sense to use this function if:

If you use reporting point backflushing, the system backflushes all material components that have been consumed and posts the activities carried out at the reporting point operation. It reduces the dependent requirements in the planned orders and updates the statistics in the LIS.

You can use either the mandatory or the optional reporting point backflush.

It makes sense to use the optional reporting point backflush if you usually only backflush at the end of the production process, but you also want to be able to backflush scrap directly at the operation. You can also use the optional reporting point backflush to calculate WIP at the end of a period.

In a mandatory reporting point backflush, you backflush the quantity currently on the production line at every reporting point. A document is created at each reporting point. The mandatory reporting point backflush guarantees maximum control of the production process. It requires, however, more effort.

When calculating WIP, the system temporarily uses the mandatory reporting point backflush process as the creation of WIP values in the optional reporting point backflush is carried out in exactly the same way as the mandatory reporting point backflush.

Prerequisites

Features

If you backflush component scrap, the system only backflushes the goods issues for the components.