Use
You can use this function when posting the goods receipt for a finished product (assembly) if the actual data of the activities used in production differs from the data specified in the routing. You can change the times of an activity, you can delete an activity or you can add another activity.
Integration
You can use this function for make-to-stock production, make-to-order production, production by lots or for kanban materials. You can also use it for reporting point backflushing.
The costs resulting from the activities are updated in Cost Object Controlling (usually at a
product cost collector.)
Prerequisites
You must create a repetitive manufacturing profile which allows the creation of actual activities.
You must assign a control key that allows backflushing and cost estimation to each operation in the routing. To do this, select Cost estimate in the control key and enter an indicator which allows backflushing in the Backflush field.

You are recommended to work with
valuated sales order stock in make-to-order production. In this case, the costs are collected at a product cost collector as in make-to-stock production.See also:
Product Cost Collector for Make-to-Order ProductionIn make-to-order production with non-valuated sales order stock, you do not collect the costs at a product cost collector but at a sales order item that carries costs and revenues. This process, however, is not recommended by SAP.
preliminary cost estimate for the production version.
Features
The system updates the actual costs at the product cost collector. Depending on the settings in the repetitive manufacturing profile, the system calculates the activity quantities on the basis of the preliminary cost estimate for the product cost collector or on the basis of the standard cost estimate for the material. You can adjust the proposed quantities to the actual activities quantities if the planned quantities differ from the actual quantities (for example, due to an unforeseen event or you may have based your planning on inaccurate estimates). The valuation of the activity quantities is carried out on the basis of the valuation variant of the current cost estimate. You save this valuation variant in Customizing Cost Object Controlling ® Periodic Product Controlling as a default value in the order type of the product cost collector.
See also:
Actual Postings in Cost Object Controlling
Valuation in Reporting Point Backflush
Recommendation for Repetitive Manufacturers