Prerequisites
You must create a work center for all the line segments you want to include in the structure of the line hierarchy. The simplest line hierarchy only consists of one line segment in which case you only have to create one work center.
Procedure
The Line Hierarchy screen appears.
If you only produce one material at a time and you enter the planned rates manually, select the No line balancing indicator.
You access the Planned rates tab page.
Result
You have created a line hierarchy which determines the master data for scheduling. For more detailed information on how to maintain line hierarchies, please refer to the SAP Documentation entitled
PP Line Design.