
Use
Along with sequencing, takt-based scheduling is a central function of the Sequencing module. Once the system determines the sequence of the planned orders for the specified planning period, it calculates the production start and finish dates and the lead time for every planned order. As opposed to lead time scheduling, the system does not use the operation times of the rate routing to calculate the lead time in Sequencing. Instead, it uses
the takt times or the production rates and the number of takts from the line hierarchy.Using takt-based scheduling, you can dispatch very large numbers of orders as the system does not have to determine the standard values from the routing nor does it have to create capacity requirements. Moreover, the system does not take the feeder lines into account when scheduling.
In flow manufacturing, the materials remain for the defined takt time in one takt of the production line for processing. The execution times calculated using the routing may vary from this takt time. Therefore, takt-based scheduling provides a more exact result for flow manufacturing than lead time scheduling.
Integration
Scheduling master data
For scheduling, the system uses the following master data which you can create and change in Line Design.
: PP Line Design; Material-Dependent Production Rate).
See also:PP Line Design; Creating Work Centers).
Other scheduling types
If you want to display capacity data, you can also carry out lead time scheduling via the routing in addition to sequencing. To do this, you can carry out an MRP run, for example and choose Lead time scheduling with capacity planning in the control parameters for scheduling. If you carry out lead time scheduling after sequencing, the system also retains the results of sequencing.
Features
Here, the system uses the maximum production rate to determine the time in which a material can be processed in one takt. This means that this time and therefore also the speed of the line is constant. You can use the planned rate to accommodate any changes to production by not placing a material on the production line in every takt.
Takt-based scheduling is clafified by the time the materials remain on the production line.
RT = (no. of takts - 1) * minimum takt time + order quantity * planned takt time
The only parameter in this type of takt-based scheduling is the planned production rate. The reciprocal value of the planned production rate determines the time in which a material can be processed in one takt. This means that this time depends on the current period and therefore the speed of the line is also variable. The reciprocal value of the planned production rate also determines the intervals in which a material is placed on the line and the intervals in which a material leaves the production line.
If you use the planned production rate for takt-based scheduling, the system calculates this retention period (RP) according to the following formula:
RT = (no. of takts - 1) * planned takt time + order quantity * planned takt time

The formulas specified here are simplified. In takt-based scheduling, the system also takes work breaks and queue times into account which may occur due to a sequence change in a sort buffer. If you change the sequence at a sort buffer, the orders in the sort buffer have to wait until the first order of the next sequence arrives at the sort buffer.
Line-on view/Line-off view), the system carries out either forward or backward/forward scheduling.
See also:
Creating Work Centers (PP Line Design)
medium-term planning period in Customizing. Activities
You can display the dates of a planned order by double-clicking the order bar in the sequence schedule.