Integrated Planning of Internal Orders 

Purpose

The integration of planning for cost centers and internal orders allows you to plan the allocation of cost center activity to orders. It also lets you plan the secondary costs that are charged to cost centers as a result of order settlement. The planning data is also passed on to Profit Center Accounting, where it used to determine the elimination of internal business sales volume.

We have already made the necessary settings for this process in Customizing. The fiscal year-dependent parameters of the plan version were maintained to enable integrated planning. Integrated planning was also activated for specific order types.

You can find more information about this process under .

Process Flow

You can find the data for this process under .

  1. Activating Integrated Planning for Orders
  2. Displaying Planned Activity Input
  3. Displaying Scheduled Activity
  4. Executing Planned Settlement
  5. Displaying Settlement Results in the Order Information System
  6. Displaying Settlement Results in the Cost Center Information System
  7. Canceling Planned Settlement