Activating Integrated Planning for Orders 
Use
This step shows some of the current settings in Customizing. Make sure that you do not make any changes in Customizing.
Procedure
Menu Path |
Tools ® AcceleratedSAP ® Customizing ® Edit Project |
Transaction Code |
SPRO, KOAI |
An overview of all existing order types appears.

Note that integrated planning is activated for order types 850 (Europe) and 851 (North America).
This indicates that orders that are assigned to these order types are involved in integrated planning. Thus all activities scheduled for these orders in the sending cost senders are automatically reported and updated in planning.
Plan price iteration valuates these plan quantities. If you change the price for an activity type, the plan-integrated orders affected are automatically revaluated.