Creating a Delivery from a Project 
Procedure
An entry screen appears.

Selection via a project definition automatically excludes simultaneous selection via a sales order. You can, however, select both a WBS element and a sales order.
Components. If there are several sales order for the chosen project, a dialog box appears. Select the sales order that the general data should be copied from.
A dialog box appears with the general data for the delivery.
Copy.The system checks the availability of the selected material components on the planned goods issue date.
A screen appears for editing the delivery items.
The system proposes the available open quantity is proposed as the default.
Result
The system then creates the delivery documents - as many as required - if different goods recipients or different delivery dates were entered. It takes all components into account whose delivery quantity is larger than zero.
You can then
display deliveries that you have created from projects in an overview.