Checking Capacity Availability in Networks 

Procedure

  1. Logistics or Accounting ® Project System ® Basic data ® Project ® Special maintenance functions ® Network ® Change.
  2. Enter the relevant data on the initial screen and choose .
  3. In the network header, choose Edit ® Availability ® Capacity.

Result

You are informed if there are work centers in the network that are overloaded. You can then display detailed information or call up finite scheduling.

For more information about the procedure for checking capacity availability, see View of Shop Floor Control (PP-SFC), in the Capacity Planning (PP-CRP) component.