Stand. Purchase Order with Configurable Model Service Specs. 
Menu Path |
From the Materials Management node, choose Purchasing ® Purchase Order ® Create ® Vendor/Supplying Plant Known |
Transaction Code |
ME21N |

You now have the option of setting default entries for the PO document. To do this, choose
Default Settings for Order Document Fields.
If you do modify your personal settings, this could mean that the entries you see on your screens might differ from those described in the IDES processes. To avoid this situation, when you have completed this process we strongly advise you to reset any changes you make to your personal settings.
Field |
Europe |
North America |
|
Standard PO |
Standard PO |
Vendor |
1104 |
1105 |
Document date |
Today’s date |
Today’s date |
.
Header.Field |
Europe |
North America |
Purchasing org. |
1000 |
3000 |
Purchasing group |
001 |
010 |
Company code |
1000 |
3000 |
Item overview.Field |
Europe |
North America |
Account assignment category |
K |
K |
Item category |
D |
D |
Delivery date |
Today’s date + 1 month |
Today’s date + 1 month |
Material group |
007 |
007 |
Plant |
1000 |
3000 |
Storage location |
0001 |
0001 |
.The system displays a warning message.
Field |
Data |
Short text |
Any |
.
Service selection.Field |
Data |
Model serv. specs. |
Select |
Right-hand field |
RV-1101 |
.
Note that on the Characteristic Evaluation screen, the characteristics Road surface in m2 and Volume of hole in m3 are not ready for input. The evaluation of these takes place using the characteristic values of the other characteristics (for example, the volume of the hole is calculated from the length, breadth, and depth of the hole: Compare with the previous activity). Furthermore, you cannot (yet) see the characteristic Kind of barrier. This characteristic is controlled by the system, so that it is appears ready for input only when the hole is deeper than 1 meter.
Field |
Data |
Location |
Produktion |
Pipe length in m |
1000 |
Pipe diameter in cm |
25 |
Transport distance in km |
10 |
Length of hole in m |
1000 |
Width of hole in m |
1,5 |
Depth of hole in m |
2 |
You can enter the value either directly, by using the F4 help, or, if any are available, you can choose from the given characteristic values. To do this, choose, for example, the characteristic Location using the F4 help and select the characteristic value you want (for example, Production area). Choose
.
.
The system now fills in the resulting values/characteristics:
Characteristic |
Value |
Description |
Pipe material |
Steel |
Pipe material should be steel when the place where work is occurring is a production area |
Road surface in m2 |
1500 |
Length * Width of the hole |
Volume of hole in m3 |
3000 |
Length * Width * Depth of the hole |
You can also see that the characteristic Kind of barrier now appears, and that it is filled with the value Shuttering wood. In the previous activity (relationships in the configuration profile) we determined that the barrier should be made of shuttering panels where the width of the hole is less than 2m (relationship ABSPERRUNG_SCHAL).
.The system now displays an information dialog box, where you can see that the value of the characteristic Pipe material was set by procedure ROHR_MATERIAL_STAHL.
Detail.In the Display Procedure: XXX dialog box, the system displays the source text for the procedure and the attributes of the characteristics that both influence ($SELF .Location) and result from ($SELF .Pipe material) the procedure. Choose
.
.You should concentrate particularly on reproducing the resulting characteristics Road surface in m2, Volume of hole in m3 and the characteristic Kind of barrier.
.
.Field |
Data |
Cost center |
4220 |
Auto repeat AA Automatic.The system automatically sets the account assignment to cost center 4220 for all the determined service lines for the PO item.
The system now displays a list of automatically selected service lines, based on the characteristic valuation you performed previously.
.
until the overview tree appears.