Prerequisites
You are in a project in the project planning board or the Project Builder.
Procedure
Choose in the |
Pushbutton/Menu Path |
Project Builder |
|
Project planning board |
Goto ® Mass change |
The Mass changes: Field view screen appears.

You can go from the field view to the table view by choosing table view. For more information on the table view, see
Executing Mass Changes with Table View.Result
The system checks the changes and executes them. A log appears. If the system could execute the changes, you can see information in the log about every object that was changed. You can display the log with one line for each entry, which is a simple confirmation, or with two lines with more details for each entry.
If the system could not execute some changes, because fields did not meet the prerequisites, the entries are highlighted in red.

You cannot save this log.
The system saves the changes when you save the project.