Executing a BOM Transfer 

Use

Preliminary requirements are created by assigning material components to the advance procurement activity in the generator network during BOM transfer. Preliminary requirements serve as coverage for real requirements that are generated at a later stage. This is useful for material components with a long replenishment lead time.

Planned independent requirements are generated (instead of reservations) for materials that are procured using MRP (item category L).

You can find further information in the SAP library under Logistics ® Project System ® Material ® Bill of Material Transfer.

Prerequisites

The following data has been maintained in Customizing for Project System:

The preliminary requirements indicator has been set.

Settings for advance procurement have been made in the material master record.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Material ® Planning ® Bill of Material Transfer

    Transaction Code

    CN33

  3. Enter the following data:
  4. Field

    Data

    Project definition

    A-20###

    Profile

    ZEC1 (IECPP: advance procurement power plant)

    Material

    IECPP-2-GE01

    Plant

    4000

    BOM usage

    1

    Additional selection criteria

    Delete

  5. Choose .
  6. In the results overview you can see the components of the multi-level BOM that will be assigned to the appropriate activities of the project due to their common reference points. The components are assigned when you save your data.

  7. Choose .

Result

After you have assigned materials IECPP-2-GE12 and IECPP-2-GE13 to the activity and the activity has been released, the system creates planned independent requirements to cover the requirements.

Branch to session two (stock/requirements list), or call up Stock/Requirements List again. Enter the material and choose .