Maintaining a Reference Point for the Network Activity 

Use

You have to maintain the reference point in the network activity in order to create a logical connection between the BOM item and the appropriate network activity (advance procurement for generator). In contrast to manual assignment of individual components, BOM changes made in the network activity in retrospect can be updated automatically.

Prerequisites

The reference point ZECPP01 (IECPP: advance procurement for power plant) is maintained in Customizing for the Project System.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Basic Data ® Project ® Project Builder

    Transaction Code

    CJ20N

  3. Open your project by double-clicking on Power Plant A-20### in the area of the screen containing the work list.
  4. Expand the following nodes in the project:
  5.  Power plant

     Components

     Generator

     Generator

    The activities flagged for deletion are underlined in blue.

  6. Select the Prel. procurement generator activity.
  7. The detail screen for the activity appears in the area of the screen containing the worklist.

  8. Choose the Assignments tab page.
  9. Enter the following data:
  10. Field

    Data

    Reference point

    ZECPP01

  11. Choose .

Result

After you have maintained the reference points, you can transfer the BOM. At this point in time, still no requirements for materials IECPP-2-GE12 and IECPP-2-GE13 have been deducted.

Since you want to check the stock situation every now and then throughout the process, call the stock/requirements list in another session (also referred to as session two in this documentation). Choose to do this.

Checking the Stock/Requirements List