Maintaining a Reference Point for the Network Activity 
Use
You have to maintain the reference point in the network activity in order to create a logical connection between the BOM item and the appropriate network activity (advance procurement for generator). In contrast to manual assignment of individual components, BOM changes made in the network activity in retrospect can be updated automatically.
Prerequisites
The reference point ZECPP01 (IECPP: advance procurement for power plant) is maintained in Customizing for the Project System.
Procedure
Menu Path |
Logistics ® Project System ® Basic Data ® Project ® Project Builder |
Transaction Code |
CJ20N |
Power Plant A-20### in the area of the screen containing the work list.
Power plant
Components
Generator
Generator

The activities flagged for deletion are underlined in blue.
Prel. procurement generator activity.The detail screen for the activity appears in the area of the screen containing the worklist.
Field |
Data |
Reference point |
ZECPP01 |
.Result
After you have maintained the reference points, you can transfer the BOM. At this point in time, still no requirements for materials IECPP-2-GE12 and IECPP-2-GE13 have been deducted.
Since you want to check the stock situation every now and then throughout the process, call the stock/requirements list in another session (also referred to as session two in this documentation). Choose
to do this.