Sample Scenario 74 

Process Flow

This example is based on a production plan in which 100 pieces are planned for <reqdat1>, <reqdat2>, and <reqdat1>.

Stage 1: Demand Management

  1. Planned independent requirements are created for the production plan. For information on how to create planned independent requirements, see Creating Planned Independent Requirements with Reference or Creating Planned Independent Requirements Without a Reference.
  2. The system finds requirements type VSEM because the strategy group has been set to 74. See the table of planning strategy assignments.

  3. The requirement is passed on to MRP. The stock/requirements list (Logistics ® Production ® MRP ® Evaluations ® Stock/reqmts list) for the assembly displays the following information:

Date

MRP element

MRP element data

Received/
required quantity

Available quantity

<today>

Stock

   

0

<today>

® Planning w/o assembly

   

<reqdat1>

IndReq

VSEM

100 -

100 -

<reqdat2>

IndReq

VSEM

100 -

200 -

<reqdat3>

IndReq

VSEM

100 -

300 -

 

Stage 2: Procurement Before Use in Production

  1. Procurement requisitions are created in the MRP run (Logistics ® Production ® MRP ® Total planning). The stock/requirements list for the assembly displays the following information:
  2. Date

    MRP element

    MRP element data

    Received/
    required quantity

    Available quantity

    <today>

    Stock

       

    0

    <today>

    ® Planning w/o assembly

       

    <reqdat1>

    PlOrd.

    1234/IndR

    100

    100

    <reqdat1>

    IndReq

    VSEM

    100 -

    0

    <reqdat2>

    PlOrd.

    1235/IndR

    100

    100

    <reqdat2>

    IndReq

    VSEM

    100 -

    0

    <reqdat3>

    PlOrd.

    1236/IndR

    100

    100

    <reqdat3>

    IndReq

    VSEM

    100 -

    0

     

    This procurement requisition is the starting point for production or external procurement. You have a variety of options for handling the procurement process. The following factors, however, are most important in this strategy:

    · At assembly level, stock is not taken into account.

    · The planned orders are not yet "real" because production of the assembly must be executed after receipt of the production order (or the schedule line in repetitive manufacturing). The planned orders are independent requirements with order type VP. This order type cannot be converted (note the Conversion field in the display of the planned order). This ensures that it is not possible to produce yet. It is impossible to convert these (VP) planned orders into production orders or to use them in a repetitive manufacturing environment.

  3. The MRP run also creates procurement requisitions for the components of the assembly (In this example, JLH-74 is the assembly). The stock/requirements list for a component displays the following information:
  4. Date

    MRP element

    MRP element data

    Received/
    required quantity

    Available quantity

    <today>

    Stock

       

    0

    <reqdat1>

    PlOrd.

    1237/Stck

    100

    100

    <reqdat1>

    DepReq

    JLH-74

    100 -

    0

    <reqdat2>

    PlOrd.

    1238/Stck

    100

    100

    <reqdat2>

    DepReq

    JLH-74

    100 -

    0

    <reqdat3>

    PlOrd.

    1239/Stck

    100

    100

    <reqdat3>

    DepReq

    JLH-74

    100 -

    0

     

  5. The main objective of this strategy (procurement for the components of the assembly) has now been reached, even without an order. In this scenario, we assume that a goods receipt (for a purchase order, for example) takes place. The stock/requirements list for all components of the final assembly displays the following information:

Date

MRP element

MRP element data

Received/
required quantity

Available quantity

<today>

Stock

   

300

<reqdat1>

DepReq

JLH-74

100 -

200

<reqdat2>

DepReq

JLH-74

100 -

100

<reqdat3>

DepReq

JLH-74

100

0

 

Stage 3: Order Requirement and Allocation

  1. Typically, a sales order is created for a finished product whose BOM uses the assembly. An order that uses the assembly is created.
  2. After a second MRP run, the stock/requirements list for the assembly displays the following information:

Date

MRP element

MRP element data

Received/
required quantity

Available quantity

<today>

Stock

   

0

<req date>

PlOrd

1233/Stck

50

50

<req date>

OrdRes

1000222

50-

0

<today>

® Planning w/o assembly

   

<reqdat1>

PlOrd.

1234/IndR

50

50

<reqdat1>

IndReq

VSEM

50 -

0

<reqdat2>

PlOrd.

1235/IndR

100

100

<reqdat2>

IndReq

VSEM

100 -

0

<reqdat3>

PlOrd.

1236/IndR

100

100

<reqdat3>

IndReq

VSEM

100 -

0

 

The independent requirements for the assembly have been consumed, resulting in reduction of the planned independent requirements.

Stage 4: Procurement After Production

  1. A reservation was therefore created one level lower, shifting the source of the requirement from the independent requirement to the sales order. The stock/requirements list of the component of the assembly displays the following information:
  2. Date

    MRP element

    MRP element data

    Received/
    required quantity

    Available quantity

    <today>

    Stock

       

    300

    <today>

    DepReq

    JLH-74

    50 -

    250

    <reqdat1>

    DepReq

    JLH-74

    50

    200

    <reqdat2>

    DepReq

    JLH-74

    100 -

    100

    <reqdat3>

    DepReq

    JLH-74

    100 -

    0

     

  3. Now a production order can be created for the assembly (Logistics ® Production ® Production control ® Order ® Create).The components are available to produce the assembly.

Stage 5: Goods Issue for Production Order

After goods issue for the production order, the stock/requirements list for the assembly looks as follows:

Date

MRP element

MRP element data

Received/
required quantity

Available quantity

<today>

Stock

   

50

<req date>

OrdRes

1000222

50-

0

<today>

® Planning w/o assembly

   

<reqdat1>

PlOrd.

1234/IndR

50

50

<reqdat1>

IndReq

VSEM

50 -

0

<reqdat2>

PlOrd.

1235/IndR

100

100

<reqdat2>

IndReq

VSEM

100 -

0

<reqdat3>

PlOrd.

1236/IndR

100

100

<reqdat3>

IndReq

VSEM

100 -

0

 

The stock/requirements list for the components of the assembly displays the following information:

Date

MRP element

MRP element data

Received/
required quantity

Available quantity

<today>

Stock

   

250

<reqdat1>

DepReq

JLH-74

50

200

<reqdat2>

DepReq

JLH-74

100 -

100

<reqdat3>

DepReq

JLH-74

100 -

0