Procedure
The initial screen for maintaining independent requirements appears.
If you want to select all requirements types, leave this field blank.
If the planned independent requirements are created using a reference, the system displays a dialog box.
– You can copy all changes in the reference.
– You can copy some of the changes. For this selection the system displays the new reference values and the current values. Select the changes you want to copy to the current independent requirements.
– You do not have to copy the changed quantities.
If the selected planned independent requirement is not created using a reference, or if no changes are made to the reference, the system displays the schedule lines screen of the planned independent requirements.