Determining Planning Quantities Using the Material Forecast 
Prerequisites
You can use the material forecast to determine planned independent requirement quantities. You must maintain the following data in the forecast screens in the material master record:
Procedure
The forecast is based on the consumption values in the material master record. The system uses the periodicity of the forecast values and the number of forecast values to be calculated as recorded in the material master record.
The Forecast Date dialog box appears.
The Forecast: Model Selection dialog box appears.
The forecast period is copied from the specification in the material master record, and cannot be changed.
The system displays a dialog box. You can choose the procedure to be used for calculating the forecast values.
The system calculates the forecast values. The systems displays the Forecast: Results dialog box. Check and, if necessary, change the forecast values.
The following model parameters and criteria for determining the accuracy of the forecast are displayed in this dialog box:
– Basic value
– Trend value
– MAD (mean absolute deviation)
– Error total
The system displays the interactive graphic. Change the graphic, if necessary.
See also:
Extended Help for Consumption-Based Planning (MM-CBP) and Managing Material Master Data (LO-MD-MM).