Copying Standard SOP Results for a Material 

Procedure

  1. Select SOP results for material in the dialog box and choose Continue.
  2. Define the reference and choose Continue.
  3. Define the transfer strategy and choose Continue.
  4. You can change the reference in Change reference values by changing the following parameters and choosing Continue.
  5. – Planned quantity

    – Postpone

    – Percentage

    Display references appears. You can check the reference quantity.

  6. Select the product group member, and choose Choose.
  7. The system copies the reference for the current material. You can check and change the quantities and dates.

  8. Select the item, and select Schedule lines.

Result

On the schedule lines screen, you can check and change the quantities and dates.

See also:

Changing PIRs.