Process Flow
This example is based on a production plan in which 100 pieces are planned for <reqdat1>, <reqdat2>, and <reqdat1>.
Stage 1: Demand Management
The system finds requirements type VSEV because the strategy group has been set to 63.
See the
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
0 | ||
<today> |
® Planning w/o assembly |
|||
<reqdat1> |
IndReq |
VSEV |
100 - |
100 - |
<reqdat2> |
IndReq |
VSEV |
100 - |
200 - |
<reqdat3> |
IndReq |
VSEV |
100 - |
300 - |
Stage 2: Procurement Before Sales
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
0 | ||
<today> |
® Planning w/o assembly |
|||
<reqdat1> |
PlOrd. |
1234/IndR |
100 |
100 |
<reqdat1> |
IndReq |
VSEV |
100 - |
0 |
<reqdat2> |
PlOrd. |
1235/IndR |
100 |
100 |
<reqdat2> |
IndReq |
VSEV |
100 - |
0 |
<reqdat3> |
PlOrd. |
1236/IndR |
100 |
100 |
<reqdat3> |
IndReq |
VSEV |
100 - |
0 |
These procurement requisitions are the starting point for production or external procurement. Various possibilities exist for handling the actual production process. The following factors, however, are important for this strategy:
· Stock is not taken into account.
· The planned orders are not yet "real," because the variant product cannot be produced until after receipt of the sales order. Technically speaking, the planned orders have order type (VP). It is impossible to convert these (VP) planned orders into production orders, or to use them in a repetitive manufacturing environment. The Conversion field in the display of the planned order is not set, which indicates that it is not possible to produce this planned order.
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
0 | ||
<reqdat1> |
PlOrd. |
1237/Stck |
100 |
100 |
<reqdat1> |
DepReq |
PLANNINGMATL |
100 - |
0 |
<reqdat2> |
PlOrd. |
1238/Stck |
100 |
100 |
<reqdat2> |
DepReq |
PLANNINGMATL |
100 - |
0 |
<reqdat3> |
PlOrd. |
1239/Stck |
100 |
100 |
<reqdat3> |
DepReq |
PLANNINGMATL |
100 - |
0 |
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
300 | ||
<reqdat1> |
DepReq |
PLANNINGMATL |
100 - |
200 |
<reqdat2> |
DepReq |
PLANNINGMATL |
100 - |
100 |
<reqdat3> |
DepReq |
PLANNINGMATL |
100 - |
0 |
Stage 3: Sales Order and Allocation
· Suppose that, for this example, an order with a quantity of 90 pieces is entered with a required delivery date of today. This order can be confirmed after the first planned independent requirement date <reqdat1>, if :
· The consumption parameters have been maintained correctly ( Consumption mode, Bwd consumption per., Fwd consumption per.) in the planning material.
· This date and the planned independent requirements can be found.
For more information, see
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
0 | ||
<orderdat1> |
Order |
00035/0010/001 |
90 - |
0 |
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
0 | ||
<today> |
® Planning w/o assembly |
|||
<reqdat1> |
PlOrd. |
1234/IndR |
100 |
100 |
<reqdat1> |
IndReq |
VSEV |
10 - |
90 |
<reqdat2> |
PlOrd. |
1235/IndR |
100 |
190 |
<reqdat2> |
IndReq |
VSEV |
100 - |
90 |
<reqdat3> |
PlOrd. |
1236/IndR |
100 |
190 |
<reqdat3> |
IndReq |
VSEV |
100 - |
90 |
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
300 | ||
<orderdat1> |
DepReq |
SZ-63 |
90 - |
210 |
<reqdat1> |
DepReq |
PLANNINGMATL |
10 - |
200 |
<reqdat2> |
DepReq |
PLANNINGMATL |
100 - |
100 |
<reqdat3> |
DepReq |
PLANNINGMATL |
100 - |
0 |
Stage 4: Procurement After Sales
Date |
MRP element |
MRP element data |
Received/ |
Available quantity |
<today> |
Stock |
0 | ||
<orderdat1> |
PlOrd. |
000335/Stck |
90 |
90 |
<orderdat1> |
Order |
00035/0010/001 |
90 - |
0 |
The planned order (‘Stck’) for the variant material can now be converted to either a production order, a process order, or allow backflushing in the repetitive manufacturing process. This triggers the production after sales order stage. Production of this material can now be executed quickly because all the necessary components are available.

Working with production orders is only one option for production. This process is also possible in the area of repetitive manufacturing.
At component level (ROH63x), the dependent requirements ("DepReq" in the planned order) are replaced by an order reservation ("OrdRes" in a production order).
Stage 5: Goods Issue for Delivery and Reduction of Planned Independent Requirements
After goods issue for the delivery of the sales order (Logistics ® Sales and distribution ® Shipping ® Delivery ® Create) for the variant material, the stock/requirements list of the "variant" material is reset back to empty again. The planned independent requirements, visible in the planning material's stock requirements list, are reduced.