Use
You can execute various functions for planning and executing projects from the Gantt chart.
Features
Function |
Icon or Menu Path |
Effect |
Schedule |
Choose Edit ® Functions ® Schedule |
Executes WBS scheduling for the selected WBS elements. |
Calculate costs |
Choose Edit ® Functions ® Calculate costs |
Executes network costing for the selected networks. See also:
Planning Costs in Networks |
Material availability |
Edit ® Functions ® Material availability (network) |
Checks material availability for all components allocated to networks, which are assigned to the selected WBS elements. See also:
Material Availability Check |
Activate purchase requisition/reservation |
Edit ® Functions ® Activate PurcReq/Resv |
Activates purchase requisitions and reservations for the selected activities. See also:
Activating Reservations and Purchase Requisitions |
Activate capacities |
Edit ® Functions ® Activate capacities |
Determines the capacity requirements for the activities assigned to the selected WBS elements, after scheduling has been executed. |
Activate cost calculation |
Edit ® Functions ® Activate cost calc. |
Determines the costs for the activities assigned to the selected WBS elements, after costing has been executed. |
Milestone trend analysis |
Choose Goto ® Milestone trend analysis |
Executes milestone trend analysis for the selected WBS elements. The prerequisites for carrying out a MTA are listed in :
Milestone Trend Analysis (MTA) |
Mass change |
Goto ® Mass change |
Makes mass changes for the selected attributes of the selected project objects. See also: Mass Change |

You can let the system search and highlight activities, for which
have not been activated. For more information, see Highlighting Project Objects