Assigning BOM Material in a Project 
Use
During quotation processing you have maintained planning material costs for the generator activity. Since the BOM for the generator material has been completely maintained, assign the material to the activity. The planning value is reduced by the value of the material.
Procedure
Menu Path |
Logistics ® Project System ® Project ® Project Builder |
Transaction Code |
CJ20N |
Power plant
Components
Generator
Generator
Checking the Planned Costs
Material planning costs have been planned for the material.
Assigning Material Components
The system displays the component overview in the work area.
Field |
Data |
Material number |
IECPP-2-GE01 |
Rqmts qty |
1 |
Item category |
L |
Recalculating Costs for the Network
Checking Costs in the Cost Element Report
The values of the cost elements have changed.
The planned costs for material planning have been reduced by the price of the material. The planned costs for the stock change (production) result from the material price from the material master record.
Result
By assigning BOM IECPP-2-GE01 to the project, the BOM has received a pegged requirement in the form of an order reservation (AR-RES).
Branch to session two (stock/requirements list), or call up the
Stock/Requirements List again. Enter the material and choose