Assignment of Formulas in the Resource 
Use
In the resource, formulas are used to calculate:
Activities
The section below describes how to access the screens on which you can enter the formulas for calculating the execution time, capacity requirements, and costs.
Execution Time
Formulas are defined on the Execution time screen area of the Scheduling tab page in resource maintenance.
For examples of formulas for calculating the execution time, see
Example Formula for the Duration of an Operation.Capacity Requirements
Formulas for calculating capacity requirements are assigned to a capacity category in the resource. This is carried out on the Capacities tab page.
Costs
Formulas for calculating internal costs are assigned to the activity types in the resource. This is carried out on the Costing tab page.

From the screens described, you can do the following: