Carrying out Execution Services 
Use
As the project progresses, you create actual costs for the costing items planned using Easy Cost Planning.
To make your work easier you trigger the required follow-up actions for the cost estimate via Execution Services direct. The system automatically selects the appropriate costing items with the required data. You normally only need to confirm the posting.
In this process you carry out the following Execution Services:
Prerequisites
You have carried out cost planning using Easy Cost Planning and released the project for the data to be posted.
Procedure
The system displays the costing structure for the project.
In the upper part of the screen you will see the checkbox Execution Service.
Carrying out Internal Activity Allocation
The system displays the costing items.
The system selects all of the costing items of category E (internal activity) and P (process costs manually), and displays them in the item area.
Posting Goods Issue
The system selects all costing items of category M (material items).
Create Purchase Requisition
The system selects all costing items of the following categories:
Field |
Data |
Plant |
1300 |
Delivery date |
14 days from today’s date |
Purchasing organization |
1000 |
Material group |
014 |
Purchasing group (PGr) |
001 |
The document is posted.
The document for the purchase requisition is displayed.
You do not need to save again. The system has already posted the document.
Result
The activity allocation, the goods issue and the purchase requisition are posted and the actual costs or the commitment are updated on the project. Check the costs in reporting.
Evaluating Costs in Reporting