Entering Notification Data for an Object in the Object List 

  1. Execute one of the following options:
    1. Select the overall completion confirmation and enter data as required in the header data section. (Refer to Using the Overall Completion Confirmation)
    2. Choose Continue.

      Choose Environment ® Object list.

    3. Choose the detail data screen for individual time confirmation for the required operation using order/operation number or using confirmation number.

On the detail data screen for the required order operation, choose Environment ® Object list.

You see the object list for the order.

  1. In the line of the required object in the list, you see:
  1. In the line of the required object in the list, choose the symbol Create notification or Change notification.

If no notification was assigned to the object, you enter the required notification category in the dialog box that appears and then choose Continue.
The header data screen for the notification appears.

If no notification was assigned to the object, the assignment of the notification to the object in the object list is only saved when you save the completion confirmation.

  1. Enter data as required in the notification.
  2. Return to the object list using Goto ® Back.
  3. If necessary, enter additional notifications/notification data for other objects in the object list and return to the confirmation transaction, from which you called up the object list, using Goto ® Back.
  4. Before you save, note the following:

    The overall completion confirmation saves all the data, which has been displayed in one step on the entry screen or the accompanying dialog boxes. It also saves proposal data.

    If you do not want to save certain confirmation or proposal data, you must delete these lines from the tables before saving.

  5. Save the completion confirmation.

See also:

Activity Report