Determining Planned Costs in Networks 

Prerequisite

Depending on what settings you have entered in the network header control data, the system automatically calculates the planned costs:

Regardless of this, you can determine the planned costs at any time, using network maintenance.

Procedure

  1. Choose Logistics or Accounting ® Project System ® Basic Data ® Project ® Special Maintenance Functions ® Network ® Change.

This brings you to the initial screen for changing networks.

  1. Enter the relevant data and choose .
  2. The Change Network: Header Data screen appears.

  3. Choose .

The system determines the costs:

Result

The system calculates the current planned costs for the network. If errors occur, the system directs your attention to the error log . You can evaluate the result of the costing directly from the network.

See Displaying Planned Costs.