Displaying Planned Costs 

Prerequisite

You can access cost analysis reports directly from your network. Different reports are available, depending on whether you access the evaluation from the network header or at activity level.

Procedure

In Header-Assigned Networks

To display the planned costs for a header-assigned network, proceed as follows:

  1. Choose Logistics or Accounting ® Project System ® Basic Data ® Project ® Special Maintenance Functions ® Network ® Change.
  2. This brings you to the initial screen for changing networks.

  3. Enter the number of the relevant network and choose .
  4. The Change Network: Header Data screen appears.

  5. You have the following alternatives:

Edit ® Costs ® Itemization or Edit ® Costs ® Cost split.

In Activity-Assigned Networks

To display the planned costs for an activity-assigned network, proceed as follows:

  1. Access the appropriate activity overview in network maintenance.
  2. Select the activity whose plan costs you want to see.
  3. Choose Edit ® Costs ® Planned/actual ® Activity/element or choose the detailed view for the activity Planned/actual costs.

You see the plan and actual costs for the activity.

Result

The plan costs are shown differently for header- and activity-assigned networks.