Prerequisites
To be able to plan overall costs for a project, you must first create a
work breakdown structure .Procedure
This brings you to the initial screen for changing cost planning.

The first time you run cost planning for a project, this automatically creates version 0.
This brings you to the screen Change Cost Planning: WBS Element Overview. It shows the project, its WBS elements, and the field ready to receive overall plan values entries.
Cost planning first refers to the overall costs which may occur for a project.
In the plan profile, you can stipulate whether cost planning is possible in all WBS elements or only in those defined as planning elements. You define planning elements in the project master data (Operative Indicators).
Annual overview or
Annual values to distribute the plan values over time.
. The system checks your cost planning. For more information, refer to
Save.