Checking Cost Planning 

Use

Having planned your costs, you can then check the plan.

Procedure

  1. Go to the screen Change Cost Planning: WBS Element Overview.
  2. Choose .
  3. The dialog box Structure Planning: Display Messages appears.

    A list is displayed, showing the WBS elements where there are planning errors. You can access error logs for the WBS elements. The logs explain what caused the errors.

  4. Close the window by choosing Continue.
  5. This returns you to the screen Change Cost Planning: WBS Element Overview.

    The WBS elements where there are planning errors are displayed in red.

  6. Correct your planning as necessary:
    1. Overwrite the incorrect plan values.
    2. Choose .
    3. Choose Save.

Result

In the event of an error, the following happens: