Confirming a Maintenance Call 

Use

When you confirm a maintenance call object (for example, technically completing a maintenance order), then the accompanying maintenance call obtains the status Completed.

However, you can also confirm a maintenance call in the scheduling function. This completion confirmation has no effect on the actual maintenance call object.

Procedure

  1. In the maintenance planning menu, choose Scheduling ® Schedule.
  2. You reach the initial screen for scheduling a maintenance plan.

  3. Enter the necessary data and choose Continue.
  4. You reach the screen for scheduling maintenance plans. The system displays the planned date that should be confirmed next in the Due planned date field.

  5. Choose Edit ® Confirm.
  6. The system highlights the Confirmation field and proposes the current date as a completion confirmation date.

  7. Save the maintenance plan.

The system confirms the maintenance call. The maintenance call obtains the status Completed.

Additional Information

The Call History

Adapting a Planned Date Individually