Rescheduling a Maintenance Plan 

Procedure

  1. In the maintenance planning menu, choose Scheduling ® Schedule.
  2. You reach the initial screen for scheduling a maintenance plan.

  3. Enter the necessary data and choose Continue.
  4. You reach the screen for scheduling maintenance plans.

  5. Choose Edit ® Update scheduling.
  6. The system calculates the maintenance calls based on the maintenance packages or maintenance cycles and the scheduling parameters. It ensures that at least one scheduling record exists that has the status On hold.

    For more information about how to cancel scheduling before saving, see Canceling Scheduling.

  7. Save the maintenance plan.

Additional Information

Adapting a Planned Date Individually

The Call History