Use
A maintenance plan can be rescheduled in the following ways:
Prerequisites
The prerequisites for rescheduling a maintenance plan depend on the
maintenance plan type. The following prerequisites apply regardless of whether it is a single cycle plan or a strategy plan.Maintenance Plan |
Prerequisites |
Time-based |
None |
Performance-based |
The overall counter reading of the counter assigned to the maintenance plan is current. If you are rescheduling a performance-based maintenance plan or a multiple counter plan, the system assumes that the counter readings are current and calculates the planned dates accordingly. |
Multiple counter plan |
Features
The system generates maintenance calls. For due maintenance calls, for example, for calls where the due date (planned date) has been reached,
maintenance call objects are generated for each due maintenance item. The system ensures that at least one maintenance call has the status On hold.Maintenance Calls
For time-based maintenance plans, the system calculates the next maintenance calls based on the
maintenance cycles or maintenance packages and the scheduling parameters.For performance-based maintenance plans and multiple counter plans, the system calculates the next maintenance calls based on the maintenance packages or maintenance cycles, the scheduling parameters, the estimated annual performance and the last counter readings.
Maintenance Call Objects
For multiple counter plans, the planned date, for which the system generates a maintenance call object, depends on the link type. In the case of an OR link, the system selects the earliest planned date. In the case of an AND link, the system will select the latest.
Note the
confirmation requirement for maintenance call objects when scheduling.