Scheduling a Performance-Based Maintenance Plan for the First Time 

Prerequisites

When you schedule a maintenance plan, the following conditions must be fulfilled:

Procedure

  1. In the maintenance planning menu, choose Scheduling ® Schedule.
  2. You reach the initial screen for scheduling a maintenance plan.

  3. Enter the number of the maintenance plan you want to schedule, and choose Continue.
  4. You reach the Maintenance Schedule screen.

  5. To start the scheduling function, choose Edit ® Start.
  6. The system displays the field Start of cycle as ready for input.

  7. Enter the counter reading at which you want scheduling to start, and choose Continue.
  8. The system automatically calculates the planned date and call date based on the maintenance packages, the scheduling parameters, the estimated annual performance and the counter reading at the start of the cycle. It then displays the following:

    - Counter reading unit

    - Counter reading at the planned date

    The first planned date cannot be in the past. If it is in the past, then the system sets the planned date as the current date.

    If necessary, you can cancel scheduling (see Canceling Scheduling).

  9. Save the scheduled maintenance plan.

Additional Information

Adapting a Planned Date Individually

Call History

Special Scheduling Functions