Usage
The purchased components were posted to the project stock. Reservations were automatically created for the components when the bill of materials (BOM) was assigned to the activity. You now require the components for the assembly. When you withdraw the components from the project stock, goods are automatically withdrawn for the reservation.
Procedure
Menu Path |
From the Materials Management node, choose Inventory Management ® Goods Movement ® Goods Issue |
Transaction Code |
MB1A |
Field |
Data |
Plant |
1300 |
Storage location |
0001 |
Field |
Data |
Network |
First network for your project T-10## |
These components are produced in-house.
An overview of the collected components appears.
Result
The goods issue is posted. This leads to a credit of WBS element T-10### and of the activity. The project stock is reduced and the reservation is reduced to zero by the activity.
Switch to session three Stock/Requirements or call up the current
Stock/Requirements List again. To evaluate the current data, chooseThe components are taken from the project stock via the goods issue for the reservation. On the network activity, the actual costs are posted using consumption cost element 890000. The stock value of the WBS element under cost element 790000 Unfinished Products is reduced accordingly.
Evaluating Goods Issue in the Cost Element Report