Posting the Goods Receipt for the Purchase Order 
Usage
The ordered materials are delivered and you enter the goods receipt.
Procedure
Menu Path |
From the Purchase order node, choose Follow-on functions ® Goods receipt. |
Transaction Code |
MIGO |
Field |
Data |
Purch.order |
Your purchase order number |
Document date |
Today’s date |
Posting date |
Today’s date |
The system transfers the purchase order data to the item overview of the goods receipt document.
Field |
Data |
Description |
Storage location |
0001 |
Material storage |

If the OK indicator is not active in the item overview, close the item detail area or set the Item OK in the lower area of the item detail.
Result
The material is posted to the project stock during goods receipt. The following applies for the current stock/requirements list:
Switch to session three Stock/Requirements or call up the current
Stock/Requirements List again. To evaluate the current data, chooseThe delivered materials are posted to the project stock. As the goods receipt is assigned to WBS element T-10###, the stock is also displayed for this WBS element only.
Evaluating Goods Receipt in the Cost Element Report