Use
In purchasing, you create a purchase order for the vendor, by selecting the assigned purchase requisitions.
Procedure
Menu Path |
From the Materials Management node, choose Purchasing ® Purchase Order ® Create ® Via PReq Assignment List |
Transaction Code |
ME58 |
Field |
Data |
Purchasing organization |
1000 |
Vendor |
1000 |
Plant |
1300 |
WBS Element |
T-10### |
The system selects the assignment list for vendor 1000.
The Create Purchase Order screen appears. In the standard, the middle part of the screen shows explanatory documentation.
The left part of the screen now shows a document overview. If it does not, choose Document Overview On. Adapt the screen area as necessary.
On the right-hand side of the screen, you see the work area for the activity.

If you want to select more than one object at the same time, keep the control key pressed whilst you make your selection.
The system transfers the items from the purchase requisition to the purchase order.
The system confirms the posting and displays a purchase order number. Make a note of this number.
Result
You have created a purchase order. The purchase order (BS-EIN) is now displayed as a receipt element in the stock/requirements list.
Switch to session three Stock/Requirements or call up the current
Stock/Requirements List again. To evaluate the current data, chooseThe purchase order causes a purchase order commitment on the project. As the purchase order items are assigned to WBS element T-10###, the commitment is also displayed for this WBS element only.
Evaluating Commitments in the Cost Element Report